Our PassiveHaus construction project

Design - hurdles - construction - permitting - results

Start Date 04/01/2010

 

 

  1. Our retirement home will be structured using PassivHaus standards to the best of our ability.
  2. This should ensure minimum expenditures for power/heating when on a fixed retirement budget.
  3. This also will substantially reduce our homes carbon footprint in relation to other similar sized homes.
  4. We are doing all sub-contracting to ensure maintaining our limited budget and our design priorities.
  5. Pictures will be posted as progress is made, with notes describing what is being shown

 

 

Project update 09/27/2011

  1. Building permit applied for - cost was 2885$ to the town -
  2. Septic DONE! - Title V Massachusetts version - cost 33,000$ plus @ 6800$ for clearing and road install.
  3. PROJECT CHANGE FROM SIPS TO ICFs
  4. Selected TRUSS and ICF manufacturers - Cost of trusses is 12400$ and cost of ICFs (10" Total EPS for all walls) is @ UNK$
  5. Footings and foundation, along with the slab scheduled to start April 30th. 
  6. The foundation will use Form-A-Drain to make drainage easy along with radon dispersal easy.
  7. Foundation ICFs 2 inches foam + 8 inches outer foam.
  8. The slab will have 4" XPS foam under all slab areas to achieve about R-value of 20-30 for slab heat retention.
  9. I ran the project through RESCHECK for the town building inspector, and it came out at 32% better than RESCHECK requirements.
  10. Septic estimates were about 25% off original sand fill due to increased perk needs according to Nashoba HD and contractor.  Costs increased by total of 8000$ overrun.
  11. Will start actual foundation work June 2/3 with leveling and filling, then FAD foundation drains for footings.
  12. Summer has been active - Trusses are up on finished ICF walls.  Radiant floor pipes in - slab done.
  13. Sheathing going up now for winter sealing.

Front Elevation

Rear Elevation

Left Elevation

Right Elevation

August images

September images

October images